Faulty equipment at Mallam substation caused Sunday dumsor – GRIDCo

The Ghana Grid Company Ltd (GRIDCo) has informed the public that on Sunday, March 3, 2024, "due to a fault" on an equipment at the Mallam substation which occurred at 20:38hrs, power supply to some customers in the western part of Accra, Winneba and Takoradi, was interrupted.
The power transmitter said its engineers "quickly isolated the faulted equipment for further investigation".
In a statement signed by Corporate Communications Manager Dzifa Bampoe, GRIDCo said restoration of supply to the affected customers started "immediately".
"As at 22:30hrs, power supply to most of the affected customers had been restored," the statement said.
It added that for areas without power supply, the engineers "are working tirelessly" to restore power once the faulted equipment is fixed.
GRIDCo "sincerely" apologised to all customers who were affected by the power supply interruption.
Source: classfmonline.com
Trending News
'Our MCE wrongfully issued a mining permit to galamseyers' – Royal Family in Tano North asserts
13:46Vice President engages Ghanaian community in Belgium
00:39Prof. Kwame Akyeampong to launch book on education reform in Africa
13:36Ghana rolls out HPV vaccine to combat cervical cancer, targeting 2.5 million girls
11:36W/R: 12 people arrested over alleged illegal mining activities that damaged Takoradi–Nsuta railway line
13:27Royal Family at Tano North accuses MCE of wrongful issuance of mining permit to galamseyers
13:37President Mahama arrives in China for high-level state visit to deepen Ghana–China relations
00:26Family of Apostle Kwadwo Safo Kantanka calls on Presidency to announce his passing
13:16Bryan Acheampong electrifies Greater Accra as grassroots declare unwavering support
10:27Ghana to host 80th anniversary of the 5th Pan -Pan-African Congress in Accra
11:16